SYSTEM MAINTENANCE: To improve your customer experience, we are performing maintenance to our systems. Manage My Account, our automated phone system and all payment systems will be unavailable starting Friday, December 13 at 8 p.m. until Sunday, December 15 at 7 a.m. Thank you for your understanding.

Please keep in mind CPS Energy will never call and threaten to disconnect or suspend service if immediate payment is not received.

Inwood/Deerfield Neighborhoods

 
 

COMMITMENT TO RELIABLE SERVICE

In an effort to continuously improve the delivery and reliability of electric service to our community, we are performing a multi-phase project to help mitigate the risk of power outages in northwest San Antonio.

 

SCOPE OF PROJECT 

The work consists of extensive tree trimming in contact with overhead lines and installing animal guards at our nearby substation. As phases of our work are completed, area residents can expect to see an improvement to the reliability of their electric service.

 

ESTIMATED TIMELINE

This project is expected to begin January 2018 and be completed by March 2018.

 

PROJECT UPDATES

01/02/2018: Reliability concerns investigated

01/04/2018: HOA meeting

01/26/2018: Project completion dates established

03/05/2018: Project completed

 

PROJECT CONTACT

For more information, please contact us at 210.353.2222